Editas Medicine Process Development Lab
Size: 2,500 SF
Construction:
Start: October 2019
Completed: June 2020
Contract Price:
Initial: $387,355
Change Orders: $1,393,261
Final: $1,780,616
Delivery Method:
Design Assist
Reference:
Denise Thomas (303) 591-2715
Design Team:
Architect
Kenny Davis (303) 960-5813
Structural Engineer
Principal Next Level, Inc.
Matt Nichols (303) 260-9456
Electrical Engineer
Matrix Technologies, Inc.
Bryan J. Curtis (419) 897-7206 ext. 262
Mechanical Engineer
Murphy Christine Beermann (303) 576-3894
Project Description:
Build out of 2,500 square feet Process Development Lab for pharmaceutical developer in the gene editing field. The project consisted of all new mechanical/HVAC systems to support a new laboratory including new exhaust system for fume hoods, new makeup in air handler, rework of existing supply and return ductwork. The electrical scope included new service entrance to the building with larger transformer from Xcel, new main distribution gear and all new branch circuitry to support the new lab and benches. The room was equipped with (4) large fume hoods, (20) custom lab benches, (12) articulating exhaust booms and (6) flammable liquid lockers. The finishes included chemical resistant flooring, washable laboratory ceiling and epoxy paint throughout.
Project Challenges:
This project initially had been managed by a third-party consultant prior to Sun being involved. The owner was not satisfied with the performance of that consultant, ultimately terminated them, and asked Sun to step in to assume control. This presented many challenges and provided opportunity to streamline the design process and allow for a more direct channel between the Owner and the construction team. Due to incomplete design packages being submitted prior to Sun’s involvement of the project, the permit drawings required numerous Addenda to clarify and correct several elements of the Mechanical and Electrical scopes of work. This meant that inspections from the AHJ would be suspended while the Addenda were under review. A strategy was employed to allow work to proceed to the next required inspections while the building department completed their reviews. Without deliberate timing of this process the project would have been brought to a complete standstill during the two separate Addendum submissions.
Cost Control Strategies:
Through consolidation of the design team, re-negotiation of prime subcontracts and a thorough re-evaluation of the design direction, Sun was able to effectively demonstrate the value of our design assist model. Budget forecasting and comprehensive competitive pricing for all unassigned scopes of work allowed the Owner to recover control of their budget.
Design Strategies: